Work Profile Report [52W266]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-2477/।।।(2)/16-01(मु0मं0घो0) /2016 दिनांक 20 सितम्बर 2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
26.60
Resanction Cost :
26.60
Tentative Cost :
5.00
Saving
21.60
Exp. Upto Last Fy :
0.62
For CFY 2025-2026
Remaining :
25.98
Demand :
2.10
Allotment :
2.10
Exp in CFY :
2.10
Total Up to Date Exp :
2.72
Alignment Approved
Sanction on : 9 years 4 months ago
20 Sep 2016
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on : 2 months 1 week from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 21.6 has been recorded as expected cost of work reduced from 26.6 to 5.00 .वनभूमि प्रस्ताव गठित, प्रतिहस्ताक्षर की कार्यवाहीं गतिमान -- as on 08-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: