Work Profile Report [52W34]

पुरोडी, रावना, डामटा मो0 मा0 का विस्तार 13 किमी0 व 20 मी0 आर0सी0सी0 सेतु का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-1754/111-2/5-64 (प्रा0आ0)/05 दि0 10.11.2005

TS Amount (lakhs) : 198.7 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

198.70

Resanction Cost :

562.53

Tentative Cost :

562.53

Exp. Upto Last Fy :

244.62

For CFY 2024-2025

Remaining :

317.91

Demand :

235.00

Allotment :

98.23

Exp in CFY :

98.23

Total Up to Date Exp :

342.85

Work completed

Sanction on : 19 years 1 month ago

10 Nov 2005

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

50 %

Tentative Completion date on : 6 months 4 days from now

30 Jun 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
13
13
13.000
0
0.000
4.250
Bridge
1 (20m)
1 (24m)
1 (24.000m)
0
0 (0.000m)
0 (0.000m)

Remark

view all

कार्य प्रगति पर है। -- as on 08-Oct-2024

Rating : 64

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: