Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 13 | 13 | 13.000 | 0 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 1 | 0 | 0 | 0 |
Span of Bridges [m] | 20 | 24 | 24.000 | 0 | 0.000 | 0.000 |
52W34 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-1754/111-2/5-64 (प्रा0आ0)/05 दि0 10.11.2005
TS Amount (lakhs) : 198.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
198.70
Resanction Cost :
562.53
Tentative Cost :
562.53
Exp. Upto Last Fy : 244.62
For CFY 2024-2025
Remaining : 317.91
Demand : 295.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 244.62
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 8 months ago
10 Nov 2005
Tentative Completion date:
2 years 1 month ago
09 Jun 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्षतिपूर्ति प्रतिकर वितरित कर दिया गया है। निविदा की कार्यवाही पूर्ण,अनुबन्ध गठन की कार्यवाही की जा रही है। -- as on 12-Jul-2024
Physical Peramenters