Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
52W369 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2274/।।।(2)19-30(प्रा0आ0) /2017 टी0सी0 दिनांक 20.06.2019 द्वारा स्वीकृत लागत रू0 20.84 लाख।
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.78
Resanction Cost :
26.78
Tentative Cost :
26.78
Exp. Upto Last Fy : 0.11
For CFY 2024-2025
Remaining : 26.67
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.11
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 3 weeks ago
20 Jun 2019
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status ---
Bottelneck: no issue
समरेखसण हेतु ग्राम मशक द्वारा अपनी भूमि मार्ग निर्माण हेतु देने से मना कर दिया गया है, विवाद सुलझा दिया गया है। समरेखण प्रस्ताव गठित कर इस कार्यालय के पत्रांक सं0-497/1सी0 दिनांक 09.07.2021 द्वारा अधीक्षण अभियन्ता नवम् वृत्त,लो0नि0वि0, देहरादून को प्रेषित। वन विभाग के साथ सुयक्त निरीक्षण किया जा चुका है। वन भूमि प्रस्ताव गठित करने की कार्यवाही गतिमान है| -- as on 21-Dec-2022
Physical Peramenters