Work Profile Report [52W385]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-2076/।।।(2)/20-47(प्रा0आ0)/ 2016 दिनंाक 24 नवम्बर 2020
TS Amount (lakhs) : 275.63 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
275.63
Resanction Cost :
275.63
Tentative Cost :
275.63
Exp. Upto Last Fy :
221.61
For CFY 2025-2026
Remaining :
54.02
Demand :
54.02
Allotment :
44.27
Exp in CFY :
43.83
Total Up to Date Exp :
265.44
Work completed
Sanction on : 4 years 8 months ago
24 Nov 2020
Physical Progress:
At start of FY 2025-2026 :
85 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह 06/2025 में कार्य पूर्ण,दायित्वोे का भुगतान शेष। -- as on 02-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: