52W443 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख्य विकास अधिकारी देहरादून के पत्रांक सं0-737/जि0यो0/2022-23 दिनांक 22.09.2022
TS Amount (lakhs) : 5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy : 4.71
For CFY 2024-2025
Remaining : 0.29
Demand : 0.29
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.71
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 9 months ago
22 Sep 2022
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
माह 06/2023 में कार्य पूर्ण। -- as on 05-Dec-2023