Work Profile Report [52W535]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-ई पत्रावली संख्या-45425 लोक निर्माण अनुभाग-2,देहरादून दिनांक 27 अक्टूबर 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
22.00
Resanction Cost :
22.00
Tentative Cost :
5.00
Saving
17.00
Exp. Upto Last Fy :
1.22
For CFY 2025-2026
Remaining :
20.78
Demand :
0.00
Allotment :
2.01
Exp in CFY :
0.00
Total Up to Date Exp :
1.22
Alignment Approved
Sanction on : 2 years 2 months ago
27 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 2 months 4 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 17 has been recorded as expected cost of work reduced from 22 to 5.00 . -- as on 02-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: