Work Profile Report : 52W615
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रावली सं0-45425 लोक निर्माण अनुभाग-2, देहरादून दिनांक 30 जनवरी 2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
126.69
Resanction Cost :
126.69
Tentative Cost :
126.69
Exp. Upto Last Fy :
0.30
For CFY 2025-2026
Remaining :
126.39
Demand :
117.00
Allotment :
50.22
Exp in CFY :
50.22
Total Up to Date Exp :
50.52
Construction Started
Sanction on : 1 year 1 week ago
30 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
40 %
Tentative Completion date on : 1 month 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.50 कि0मी0 पहाड़ कटान का कार्य पूर्ण, शेष कार्य प्रगति पर है। -- as on 07-Jan-2026