Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7.000 | 0 | 0.000 | 0.000 |
52W79 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1376/111 (2)/09-06 (मा0मु0घो0)/08 टी0सी0-1 दि0 23.3.10
TS Amount (lakhs) : 245 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
245.00
Resanction Cost :
245.00
Tentative Cost :
245.00
Exp. Upto Last Fy : 239.48
For CFY 2024-2025
Remaining : 5.52
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 239.48
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
14 years 3 months ago
23 Mar 2010
Tentative Completion date:
5 years 7 months ago
05 Dec 2018
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
माह 02/2019 में कार्य पूर्ण, दायित्वों का भगतान शेष। -- as on 31-Jul-2020
Physical Peramenters