Work Profile Report [52W8]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-533/लो0नि0-1/2003-16 (प्रा0आ0)/03 दि0 18.08.2003
TS Amount (lakhs) : 194.35 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
194.35
Resanction Cost :
194.35
Tentative Cost :
194.35
Exp. Upto Last Fy :
185.10
For CFY 2024-2025
Remaining :
9.25
Demand :
2.25
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
185.10
Work completed
Sanction on : 21 years 4 months ago
18 Aug 2003
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 5 months ago
30 Jun 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह 02/2020 में कार्य पूर्ण दायित्व का भुगतान शेष। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI: