Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11 | 11 | 0.000 | 11 | 0.000 | 0.000 |
53W1176 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 341/।।।(2)/17-23 (एम0एल0ए0)/2017 दिनांक 02.06.2017
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 90.20 Lacs
Resanction Cost : 90.20 Lacs
Exp. Upto Last Fy : 9.52 Lacs
For CFY 2024-2025
Remaining : 80.68 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.52 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
6 years 11 months ago
02 Jun 2017
Tentative Completion date:
10 months 2 weeks from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
दिनांक 10.04.2024 को प्रभागीय वनाधिकारी, देहरादून वन प्रभाग, देहरादून द्वारा प्रस्ताव आपत्तियों के निराकरण हेतु खण्ड में वापस लौटाया गया है। आपत्तियों के निराकरण के पश्चात इस कार्यालय के पत्रांक 1139/1 सी दिनांक 24.04.2024 को प्रभागीय वनाधिकारी देहरादून को प्रेषित। -- as on 04-May-2024
Physical Peramenters