Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.045 | 1.895 | 1.890 | 0.0050000000000001 | 0.000 | 0.000 |
53W1523 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2356/।।।(2)/21-03(प्रा0आ0)2018 दिनांक 02.08.2021
TS Amount (lakhs) : 135.92 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
135.92
Resanction Cost :
135.92
Tentative Cost :
135.92
Exp. Upto Last Fy : 130.97
For CFY 2024-2025
Remaining : 4.95
Demand : 4.95
Allotment : 4.95
Exp in CFY : 0.00
Total Up to Date Exp : 130.97
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
02 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य माह 07/2023 में पूर्ण। -- as on 01-May-2024
Physical Peramenters