Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.1 | 3.1 | 3.100 | 0 | 0.000 | 0.000 |
53W1528 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2396/।।।(2)/21-19(एम0एल0ए0)2017 दिनांक 04.08.2021
TS Amount (lakhs) : 35.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.89
Resanction Cost :
35.89
Tentative Cost :
35.89
Exp. Upto Last Fy : 12.82
For CFY 2024-2025
Remaining : 23.07
Demand : 23.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 12.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
2 years 4 months ago
28 Feb 2022
Remark
Bottelneck: no issue
एस0डी0बी0सी0 का कार्य माह 02/2022 में पूर्ण। -- as on 25-May-2022