Work Profile Report [53W1534]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2396/।।।(2)/21-19(एम0एल0ए0)2017 दिनांक 04.08.2021
TS Amount (lakhs) : 92.86 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
92.86
Resanction Cost :
92.86
Tentative Cost :
92.86
Exp. Upto Last Fy :
91.18
For CFY 2024-2025
Remaining :
1.68
Demand :
1.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
91.18
Work completed
Sanction on : 3 years 3 months ago
04 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date : 1 year 7 months ago
31 Mar 2023
Physical Linear Components
Remark
कार्य माह 06/2022 में पूर्ण। -- as on 28-Jul-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand