Work Profile Report [53W1549]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 4039/।।।(2)/21-19(एम.एल.ए.)2017 टी0सी0 दिनांक 20.09.2021
TS Amount (lakhs) : 55.8 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
55.80
Resanction Cost :
55.80
Tentative Cost :
55.80
Exp. Upto Last Fy :
54.91
For CFY 2024-2025
Remaining :
0.89
Demand :
0.80
Allotment :
0.77
Exp in CFY :
0.77
Total Up to Date Exp :
55.68
Work completed
Sanction on : 3 years 3 months ago
20 Sep 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date : 1 year 8 months ago
31 Mar 2023
Physical Linear Components
Remark
कार्य माह 11/22 में पूर्ण। -- as on 15-Dec-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand