Work Profile Report [53W1611]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी देहरादून का पत्रांक 861/जि0यो0-लो0नि0वि0/2022-23 दिनांक 17-10-2022
TS Amount (lakhs) : 3 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
3.00
Demand :
3.00
Allotment :
3.00
Exp in CFY :
2.93
Total Up to Date Exp :
2.93
Work completed
Sanction on : 2 years 1 month ago
17 Oct 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य माह 03/2024 में पूर्ण। -- as on 01-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand