Work Profile Report [53W1622]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 1530ध्।।।(3)ध्2022-01(वि0स0यो0) 2021 दिनांक 28.12.2022
TS Amount (lakhs) : 978.14 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
601.68
Resanction Cost :
601.68
Tentative Cost :
601.68
Exp. Upto Last Fy :
545.57
For CFY 2024-2025
Remaining :
56.11
Demand :
56.00
Allotment :
56.00
Exp in CFY :
52.45
Total Up to Date Exp :
598.02
Work completed
Sanction on : 1 year 11 months ago
28 Dec 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग कार्य माह 11/2023 में पूर्ण। -- as on 07-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: