Administrative Approval Detail : शासनादेश ई पत्रावली सं0 54048 दिनांक 14.07.2023
TS Amount (lakhs) : 76.32 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.32
Resanction Cost :
76.32
Tentative Cost :
76.32
Exp. Upto Last Fy :
35.95
For CFY 2024-2025
Remaining :
40.37
Demand :
40.00
Allotment :
40.37
Exp in CFY :
40.60
Total Up to Date Exp :
76.55
Work completed
Sanction on : 1 year 5 months ago
14 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
100 %
Tentative Completion date on : 4 months 2 weeks ago
08 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य माह 09/2024 में पूर्ण । -- as on 15-Oct-2024