Work Profile Report [53W1664]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 50232 दिनांक 13.10.2023
TS Amount (lakhs) : 247.67 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
247.67
Resanction Cost :
247.67
Tentative Cost :
247.67
Exp. Upto Last Fy :
50.27
For CFY 2024-2025
Remaining :
197.40
Demand :
190.00
Allotment :
150.00
Exp in CFY :
79.63
Total Up to Date Exp :
129.90
Construction Started
Sanction on : 1 year 1 month ago
13 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
57 %
Tentative Completion date on : 2 months 1 week from now
06 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नाली निर्माण, जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand