Work Profile Report [53W1689]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012 दिनांक 25.09.2023
TS Amount (lakhs) : 41.58 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.58
Resanction Cost :
41.58
Tentative Cost :
41.58
Exp. Upto Last Fy :
2.47
For CFY 2024-2025
Remaining :
39.11
Demand :
39.00
Allotment :
39.00
Exp in CFY :
32.02
Total Up to Date Exp :
34.49
Construction Started
Sanction on : 1 year 1 month ago
25 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
87 %
Tentative Completion date on : 1 day 4 hours from now
25 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: