Administrative Approval Detail : शासनादेश ई पत्रावली सं0 46690 दिनांक 15.03.2024
TS Amount (lakhs) : 157.18 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
157.18
Resanction Cost :
168.69
Tentative Cost :
168.69
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
168.69
Demand :
100.00
Allotment :
50.00
Exp in CFY :
10.42
Total Up to Date Exp :
10.42
Construction Started
Sanction on : 9 months 1 week ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
5 %
Tentative Completion date on : 1 year 3 months from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड कटान का कार्य प्रगति पर है । -- as on 04-Dec-2024