Work Profile Report [53W1703]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012/23 दिनांक 06.06.2024
TS Amount (lakhs) : 29.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.11
Resanction Cost :
29.11
Tentative Cost :
29.11
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
29.11
Demand :
29.11
Allotment :
25.00
Exp in CFY :
20.09
Total Up to Date Exp :
20.09
Construction Started
Sanction on : 5 months 2 weeks ago
06 Jun 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
40 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग पर इण्टरलॉकिग टाईल्स लगाने का कार्य प्रगति पर है। -- as on 15-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand