Work Profile Report [53W1780]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012 दिनांक 04.08.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1306.64
Resanction Cost :
1306.64
Tentative Cost :
1306.64
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
1,306.64
Demand :
600.00
Allotment :
225.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 5 months 2 weeks ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
5 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग पर खुदाई, जी0सी0बी0, डब्लू0एम0एम0 का कार्य प्रगति पर है। -- as on 08-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: