Work Profile Report [54W1107]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0- 52ध्।।।(3)ध्2021-07 (एन0एच0)2016, लोक निर्माण अनुभाग-3, देहरादून, दिनांक 12.01.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Important Works ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4315.57
Resanction Cost :
4315.57
Tentative Cost :
4315.57
Exp. Upto Last Fy :
3,350.00
For CFY 2024-2025
Remaining :
965.57
Demand :
965.57
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3,350.00
Construction Started
Sanction on : 3 years 11 months ago
12 Jan 2021
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
60 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य एन0एच0ए0आई0 के द्वारा करवाया जा रहा है। कार्य की भौतिक प्रगति 60 प्रतिशत है। -- as on 05-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand