Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.947 | 1.947 | 1.940 | 0.0070000000000001 | 0.000 | 0.000 |
54W1160 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 शा0सं0-।/111277/2023 (ई पत्रावली संख्या-49995), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 29.03.2023
TS Amount (lakhs) : 79.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
79.03
Resanction Cost :
79.03
Tentative Cost :
79.03
Exp. Upto Last Fy : 76.34
For CFY 2024-2025
Remaining : 2.69
Demand : 2.69
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 76.34
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
4 months 1 week ago
05 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 08-Apr-2024
Physical Peramenters