Work Profile Report [54W1182]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन का पत्रांक ।/163240ध्2023, (ई पत्रावली संख्या- 60170) लोक निर्माण अनुभाग-2, देहरादून, दिनांक 19.10.2023
TS Amount (lakhs) : 350.1 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
350.10
Resanction Cost :
350.10
Tentative Cost :
350.10
Exp. Upto Last Fy :
181.25
For CFY 2024-2025
Remaining :
168.85
Demand :
168.85
Allotment :
8.07
Exp in CFY :
8.07
Total Up to Date Exp :
189.33
Construction Started
Sanction on : 9 months 4 weeks ago
19 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
85 %
Up to Date :
85 %
Tentative Completion date on : 1 week 6 days from now
30 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग कार्य पूर्ण। साइनेज का कार्य प्रगति पर है। -- as on 05-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: