Work Profile Report [54W1222]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/171460/2023 (ई पत्रावली सं0-50023), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 29.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.60
Resanction Cost :
6.60
Tentative Cost :
6.60
Exp. Upto Last Fy :
0.19
For CFY 2024-2025
Remaining :
6.41
Demand :
6.41
Allotment :
3.00
Exp in CFY :
2.89
Total Up to Date Exp :
3.08
Construction Started
Sanction on : 11 months 3 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
1 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 26-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: