Work Profile Report [54W1233]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रांक ।/197952/2024 (पत्रावली संख्या 47588), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 13-03-2024
TS Amount (lakhs) : 117.47 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
117.47
Resanction Cost :
117.47
Tentative Cost :
117.47
Exp. Upto Last Fy :
0.26
For CFY 2024-2025
Remaining :
117.21
Demand :
117.21
Allotment :
49.68
Exp in CFY :
35.82
Total Up to Date Exp :
36.08
Construction Started
Sanction on : 9 months 4 weeks ago
13 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
35 %
Tentative Completion date on : 3 days 16 hours ago
09 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 04-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand