Work Profile Report [54W725]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3279/।।।(2)/17-16(एम0एल0ए0) / 2015, लोक निर्माण अनुभाग-2, दिनांक 03.01.2017
TS Amount (lakhs) : 217.52 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
217.52
Resanction Cost :
217.52
Tentative Cost :
217.52
Exp. Upto Last Fy :
193.08
For CFY 2024-2025
Remaining :
24.44
Demand :
24.43
Allotment :
21.56
Exp in CFY :
21.56
Total Up to Date Exp :
214.64
Work completed
Sanction on : 7 years 11 months ago
03 Jan 2017
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 years 7 months ago
30 Apr 2019
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष है। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI: