Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
54W730 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5150(1)/।।।-2/10-18(प्रा0आ0)/10, दिनांक 16.08.2010
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 37.80
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
13 years 11 months ago
16 Aug 2010
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
भारत सरकार के पत्रांक 8बी0/यू0सू0पी0/06/133/2021/एफ0सी0/1481, दिनांक 01.02.2023 द्वारा वन भूमि प्रकरण को मैरिट के आधार पर निरस्त कर दिया गया है। -- as on 07-Jun-2024
Physical Peramenters