Work Profile Report [54W742]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5762/।।।(2)/14-05 (मा0मु0घो0)/2014, दिनांक 17.10.2014
TS Amount (lakhs) : 66 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.00
Resanction Cost :
66.00
Tentative Cost :
66.00
Exp. Upto Last Fy :
4.13
For CFY 2024-2025
Remaining :
61.87
Demand :
1.12
Allotment :
1.12
Exp in CFY :
1.12
Total Up to Date Exp :
5.25
Construction Started
Sanction on : 10 years 1 month ago
17 Oct 2014
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन प्रभाग, कालसी से संयुक्त निरीक्षण की तिथि निर्धारण की सूचना विभाग को प्राप्त नहीं हुई है। -- as on 30-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: