Work Profile Report [55W1499]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 1637/।।।(2)/20-35(एम.एल.ए.) /2017 टी0सी0 दिनांक 04.09.2020
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
125.79
Resanction Cost :
125.79
Tentative Cost :
125.79
Exp. Upto Last Fy :
122.10
For CFY 2024-2025
Remaining :
3.69
Demand :
0.60
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
122.10
In Maintenance After Completion
Sanction on : 4 years 3 months ago
04 Sep 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण । अनुरक्षण का कार्य कराया जायेगा, जिस हेतु धनावंटन की मांग की गयी है। -- as on 15-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand