Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.65 | 1.65 | 1.000 | 0.65 | 0.650 | 0.300 |
55W1833 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/139598/2023/PWD2-BUD-ANBU/25/2023-III-2-Public Works Department
TS Amount (lakhs) : 92.1 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.10
Resanction Cost :
92.10
Tentative Cost :
92.10
Exp. Upto Last Fy : 12.09
For CFY 2024-2025
Remaining : 80.01
Demand : 40.00
Allotment : 10.00
Exp in CFY : 5.96
Total Up to Date Exp : 18.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 75 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
1 week 2 days from now
27 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.30 कि0मी0 में मार्ग कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 28-May-2024
Physical Peramenters