Work Profile Report [55W1839]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 1/142766/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 89.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
97.76
Resanction Cost :
97.76
Tentative Cost :
87.76
Saving
10.00
Exp. Upto Last Fy :
57.29
For CFY 2024-2025
Remaining :
40.47
Demand :
30.00
Allotment :
20.00
Exp in CFY :
0.11
Total Up to Date Exp :
57.40
Work completed
Sanction on : 1 year 1 week ago
03 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 2 months 1 day ago
15 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 05/2024 -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: