Work Profile Report [55W1875]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 17.45 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
17.45
Resanction Cost :
17.45
Tentative Cost :
17.45
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
17.35
Demand :
3.00
Allotment :
13.47
Exp in CFY :
13.47
Total Up to Date Exp :
13.57
Work completed
Sanction on : 1 year 1 month ago
17 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 day from now
25 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 10/2024 -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand