Work Profile Report [55W1878]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 27.61 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
27.61
Resanction Cost :
27.61
Tentative Cost :
17.61
Saving
10.00
Exp. Upto Last Fy :
20.72
For CFY 2025-2026
Remaining :
6.89
Demand :
0.00
Allotment :
4.72
Exp in CFY :
0.00
Total Up to Date Exp :
20.72
Work completed
Sanction on : 1 year 8 months ago
17 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 1 year 3 months ago
31 Mar 2024
Physical Linear Components
Remark
कार्यपूर्ण दायित्व शेष। -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: