Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 3.000 |
55W1880 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/164802/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 291.42 Lacs
Financial Detail
Sanction Cost : 291.42 Lacs
Resanction Cost : 291.42 Lacs
Exp. Upto Last Fy : 50.23 Lacs
For CFY 2024-2025
Remaining : 241.19 Lacs
Demand : 181.50 Lacs
Allotment : 148.00 Lacs
Exp in CFY : 147.92 Lacs
Total Up to Date Exp : 198.15 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 95 %
Sanction on :
7 months 6 days ago
27 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग कार्य पूर्ण, पटरी आदि कार्य प्रगति में है। -- as on 28-May-2024