Work Profile Report [55W1890]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O.No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 41.03 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.03
Resanction Cost :
41.03
Tentative Cost :
25.10
Saving
15.93
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
40.93
Demand :
25.00
Allotment :
27.32
Exp in CFY :
27.32
Total Up to Date Exp :
27.42
Work completed
Sanction on : 11 months 1 week ago
12 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
2 %
Up to Date :
100 %
Tentative Completion date on : 2 months 1 week ago
15 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 09/2024 -- as on 30-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: