Work Profile Report [55W1892]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 43.64 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.64
Resanction Cost :
43.64
Tentative Cost :
40.00
Saving
3.64
Exp. Upto Last Fy :
0.71
For CFY 2024-2025
Remaining :
42.93
Demand :
33.90
Allotment :
35.89
Exp in CFY :
35.89
Total Up to Date Exp :
36.60
Work completed
Sanction on : 1 year 1 week ago
12 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
100 %
Tentative Completion date on : 4 months 5 days ago
20 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 07/2024 -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand