Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.000 | 0.6 | 0.600 | 0.600 |
55W1894 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 32.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.38
Resanction Cost :
32.38
Tentative Cost :
32.38
Exp. Upto Last Fy : 0.08
For CFY 2024-2025
Remaining : 32.30
Demand : 25.00
Allotment : 21.86
Exp in CFY : 26.49
Total Up to Date Exp : 26.57
Work completed
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 100 %
Sanction on :
7 months 5 days ago
12 Dec 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024 -- as on 29-Jun-2024
Physical Peramenters