Work Profile Report [55W1895]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 1/175558/2023/पीडब्लूडी2-बीयूडी/ एएनबीयू/36/2023-।।।-2-लो0नि0वि0
TS Amount (lakhs) : 86.78 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
86.78
Resanction Cost :
86.78
Tentative Cost :
80.08
Saving
6.70
Exp. Upto Last Fy :
0.08
For CFY 2024-2025
Remaining :
86.70
Demand :
80.00
Allotment :
60.00
Exp in CFY :
13.07
Total Up to Date Exp :
13.15
Construction Started
Sanction on : 7 months 4 weeks ago
19 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
95 %
Tentative Completion date on : 4 weeks 1 day from now
15 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 6.7 has been recorded as expected cost of work reduced from 86.78 to 80.08 . -- as on 01-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: