Work Profile Report [55W1905]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : G.O.No. 1/164806/2023 PWD2-BUD/1/2023-III-2-Public Works Department
TS Amount (lakhs) : 43.54 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.54
Resanction Cost :
43.54
Tentative Cost :
35.12
Saving
8.42
Exp. Upto Last Fy :
0.12
For CFY 2024-2025
Remaining :
43.42
Demand :
35.00
Allotment :
20.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.12
Construction Started
Sanction on : 9 months 2 weeks ago
27 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
2 %
Up to Date :
30 %
Tentative Completion date on : 2 months 1 week from now
30 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.80 कि0मी0 में इंटर कोट तक कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: