Work Profile Report [55W1907]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 1/186272/2024/पीडब्लूडी2-बीयूडी/ एएनबीयू/36/2023-।।।-2-लो0नि0वि0
TS Amount (lakhs) : 69.67 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
69.67
Resanction Cost :
69.67
Tentative Cost :
55.00
Saving
14.67
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
69.67
Demand :
55.00
Allotment :
50.00
Exp in CFY :
17.81
Total Up to Date Exp :
17.81
Construction Started
Sanction on : 6 months 2 weeks ago
31 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
1 %
Up to Date :
38 %
Tentative Completion date on : 1 day 32 minutes ago
15 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.63 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: