Work Profile Report [55W1950]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/241293/2024/PWD2-BUD/ANBU/32/2023-III-2-Public Works Department
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
69.60
Resanction Cost :
69.60
Tentative Cost :
69.60
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
69.60
Demand :
30.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
in Tendering Stage
Sanction on : 2 months 4 days ago
19 Sep 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबंध गठन में है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: