Work Profile Report : 55W1977
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/261888/2024/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department-Part(1)
TS Amount (lakhs) : 56.51 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.51
Resanction Cost :
56.51
Tentative Cost :
56.51
Exp. Upto Last Fy :
2.42
For CFY 2025-2026
Remaining :
54.09
Demand :
10.43
Allotment :
26.51
Exp in CFY :
26.51
Total Up to Date Exp :
28.93
Construction Started
Sanction on : 1 year 1 month ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
35 %
Tentative Completion date on : 6 months 2 weeks from now
31 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.20 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 03-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: