Work Profile Report [55W1992]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G. O. 840/III(3)/2025-05(CRIF)/2025/E-88887
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3115.77
Resanction Cost :
3115.77
Tentative Cost :
2900.30
Saving
215.47
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
3,115.77
Demand :
713.26
Allotment :
1,246.30
Exp in CFY :
118.66
Total Up to Date Exp :
118.66
Construction Started
Sanction on : 6 months 1 week ago
11 Jul 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
5 %
Tentative Completion date on : 1 year 1 week from now
31 Jan 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 215.47 has been recorded as expected cost of work reduced from 3115.77 to 2900.3 . -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: