Work Profile Report [55W2029]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/320044/25/PWD2-BUD/ANBU/19/2023-III-2-Public Works Department Dt. 06-08-2025
TS Amount (lakhs) : 54.21 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
54.21
Resanction Cost :
54.21
Tentative Cost :
54.21
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
54.21
Demand :
37.62
Allotment :
17.54
Exp in CFY :
17.54
Total Up to Date Exp :
17.54
Construction Started
Sanction on : 5 months 2 weeks ago
06 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 2 months 1 week from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.40 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 30-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: