Work Profile Report : 55W2031
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/320044/25/PWD2-BUD/ANBU/19/2023-III-2-Public Works Department Dt. 06-08-2025
TS Amount (lakhs) : 82.27 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
82.27
Resanction Cost :
82.27
Tentative Cost :
82.27
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
82.27
Demand :
19.15
Allotment :
0.30
Exp in CFY :
0.15
Total Up to Date Exp :
0.15
Construction Started
Sanction on : 6 months 6 days ago
06 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
20 %
Tentative Completion date on : 4 months 2 weeks from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.20 कि0मी0 में टाॅपकोट तक व 0.10 कि0मी0 में टाईल्स कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 27-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: