Work Profile Report [55W2043]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/327152/2025/PWD2-BUD/ANBU/15/2024-III-2-Public Works Department Dt. 02-09-2025
TS Amount (lakhs) : 106.05 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
106.05
Resanction Cost :
106.05
Tentative Cost :
106.05
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
106.05
Demand :
56.31
Allotment :
40.35
Exp in CFY :
40.35
Total Up to Date Exp :
40.35
Construction Started
Sanction on : 4 months 3 weeks ago
02 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
55 %
Tentative Completion date on : 4 months 3 weeks from now
15 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.80 कि0मी0 में टाॅपकोट तक कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 31-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand