Work Profile Report [56W163]

शम्भू की चैकी पंजिया बनसार धैरालानी मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0 6406/।।। (2) 10-19 (मु0मं0घो0)/2009 दिनांक 29-10-2010

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.40

Resanction Cost :

50.40

Tentative Cost :

50.40

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

50.40

Demand :

0.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Unstarted Work

Sanction on : 13 years 9 months ago

29 Oct 2010

Physical Progress:

At start of FY 2024-2025 :

5 %

Up to Date :

5 %

Tentative Completion date on : 2 years 4 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
4
-

Remark

view all

ग्राम जुटिया द्वारा समरेंखण पर विवाद किया जा रहा हैं, जिसे सुलझााने का प्रयास किया जा रहा हैं। पुनः माह जुलाई में सर्वेक्षण कार्य किया गया परन्तु पुनः ग्रामवासियों द्वारा विवाद किया गया हैं। -- as on 06-Oct-2022

Rating : 5

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: