Work Profile Report [56W19]

डाडा टिकरी देसऊ देऊ मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

48.60

Resanction Cost :

48.60

Tentative Cost :

48.60

Exp. Upto Last Fy :

0.36

For CFY 2025-2026

Remaining :

48.24

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.36

Alignment Approved

Sanction on : 18 years 9 months ago

25 Sep 2006

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

10 %

Tentative Completion date on : 8 months 2 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
3
-

Remark

view all

समरेंखण स्वीकृत है। परन्तु ग्रामवासियों द्वारा पुनः विवाद किया जा रहा हैं। -- as on 20-Apr-2023

Rating : 11

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: